工商业式光伏项目开发(并网、验收阶段)

  1. 并网验收阶段
    10.1. 第1阶段进行项目评估与合同签订,
    10.2. 第2阶段办理备案与接入手续,
    10.3. 第3阶段建设并网。
    10.4. 项目业主向电网公司提出并网验收和调试申请
    10.5. 电网公司受理并网验收和调试申请
    10.6. 与电网签订购售电合同和并网调度协议
    10.7. 安装关口电能计量装置
    10.8. 完成并网验收及调试
  2. 并网流程
    11.1. 提出并网申请
    11.2. 电力局受理并网申请后
    11.3. 制订系统接入方案
    11.4. 双方确认接入方案
    11.5. 由电力局出具接入意见函
    11.6. 根据项目标准及工程建设
    11.7. 提出并网验收及调试申请
    11.8. 然后受理并网验收及调试申请
    11.9. 安装电能计量装置
    11.10. 签订购售电合同及并网调度协议
    11.11. 并展开并网验收调试
    11.12. 最后并网运行

△Disclaimer:

Some of the above pictures and information are from the Internet, and the copyright belongs to the original author and his company; this article is for study and research purposes only and cannot be used for commercial purposes. If this article infringes your rights, please contact us to delete; some articles The original author could not be contacted due to various reasons during the push. If copyright issues are involved, the original author is kindly requested to contact us and deal with it immediately.